pmi PMP Exam Questions
Questions for the PMP were updated on : Dec 14 ,2024
Question 1
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
An element of the project scope statement is:
-
A. Acceptance criteria.
-
B. A stakeholder list.
-
C. A summary budget.
-
D. High-level risks.
Answer:
A
Explanation:
Reference:
Question 2
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
Which document describes the necessary information to determine if a project is worth the required investment?
-
A. Cost baseline
-
B. Service level agreement
-
C. Memorandum of understanding
-
D. Business case
Answer:
D
Explanation:
Reference:
Question 3
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
Which input to the Plan Risk Management process provides information on high-level risks?
-
A. Project charter
-
B. Enterprise environmental factors
-
C. Stakeholder register
-
D. Organizational process assets
Answer:
A
Explanation:
Reference:
Question 4
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
Which item is an example of personnel assessment?
-
A. Resource calendar
-
B. Tight matrix
-
C. Team-building activity
-
D. Focus group
Answer:
D
Explanation:
Reference:
Question 5
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved
in a project?
-
A. Feedback analysis
-
B. Stakeholder analysis
-
C. Communication management plan
-
D. Stakeholder management plan
Answer:
D
Explanation:
Reference:
Question 6
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
Which input to the Identify Stakeholders process provides information about internal or external parties related to the
project?
-
A. Procurement documents
-
B. Communications plan
-
C. Project charter
-
D. Stakeholder register
Answer:
C
Explanation:
Reference:
Question 7
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
The Identify Stakeholders process is found in which Process Group?
-
A. Initiating
-
B. Monitoring and Controlling
-
C. Planning
-
D. Executing
Answer:
A
Explanation:
Reference:
Question 8
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
An input to Develop Project Charter is a/an:
-
A. Business case.
-
B. Activity list.
-
C. Project management plan.
-
D. Cost forecast.
Answer:
A
Explanation:
Reference:
Question 9
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a
project?
-
A. Project Risk Management
-
B. Project Human Resource Management
-
C. Project Scope Management
-
D. Project Stakeholder Management
Answer:
D
Explanation:
Reference:
Question 10
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
-
A. Stakeholder register
-
B. Scope management plan
-
C. Stakeholder management plan
-
D. Project charter
Answer:
A
Explanation:
Reference:
Question 11
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
In which Knowledge Area is the project charter developed?
-
A. Project Cost Management
-
B. Project Scope Management
-
C. Project Time Management
-
D. Project Integration Management
Answer:
D
Explanation:
Reference:
Question 12
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
The ability to influence cost is greatest during which stages of the project?
-
A. Early
-
B. Middle
-
C. Late
-
D. Completion
Answer:
A
Explanation:
Reference:
Question 13
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
Which process involves developing an approximation of the monetary resources needed to complete project activities?
-
A. Estimate Costs
-
B. Control Costs
-
C. Determine Budget
-
D. Plan Cost Management
Answer:
A
Explanation:
Reference:
Question 14
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
Which tool or technique is used in the Develop Project Management Plan process?
-
A. Pareto diagram
-
B. Performance reporting
-
C. SWOT analysis
-
D. Expert judgment
Question 15
Topic 1, Initiation (This topic also includes exam content outline.)
Topic 1
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
-
A. Responses
-
B. Appetite
-
C. Tolerance
-
D. Attitude