Page 1 out of 27. Viewing questions 1-15 out of 402
Question 1
Topic 1
Topic 1 A project manager has failed to obtain the necessary permits from the local building commission. The project has been stopped because of a failure to understand the importance of:
A. internal process compliance.
B. risk avoidance.
C. standards compliance.
D. audit trail compliance.
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 2
Topic 1
Topic 1 In which of the following organization types would a project manager have the MOST authority?
A. Projectized
B. Balanced Matrix
C. Weak Matrix
D. Functional
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 3
Topic 1
Topic 1 Which of the following steps should a project manager take to ensure the quality of project deliverables for a customer? (Select Two).
A. The project manager should consult the project sponsor and customer to review the current quality requirements.
B. The project manager should request a peer review of the project to determine if it meets the customers quality standards.
C. The project manager should change the scope of the project to meet the customers expectations of quality standards.
D. The project manager should check the finished product to determine if it meets the customers quality standards.
E. The project manager should outsource to obtain the best resources for the project.
Answer:
B D
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 4
Topic 1
Topic 1 A project manager has a project with staff in four different countries. When generating the resource management plan, which of the following should be considered FIRST?
A. Reviewing holiday and vacation schedule with all team members.
B. Getting the email address of all the employees.
C. Locating each employee on the map in the office.
D. Understanding the international country code of all the team members.
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 5
Topic 1
Topic 1 Which of the following occurs during a project kick-off meeting? (Select Two).
A. Work performance information is established.
B. Risk analysis is performed.
C. Quality metrics are defined.
D. Project goals are communicated.
E. Roles and responsibilities of the project team are identified.
Answer:
D E
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 6
Topic 1
Topic 1 Which of the following should be created in the project closing documentation? (Select Two).
A. Closure report summarizing costs
B. Responsibility assessment matrix
C. Lessons learned
D. Project timeline
E. Statement of Work (SOW)
Answer:
A C
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 7
Topic 1
Topic 1 Which of the following methods would a project manager use to estimate the construction cost of a 2,000 square foot home when given the cost per square foot?
A. Parametric estimating
B. Analogous estimating
C. Top-down estimating
D. Bottom-up estimating
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 8
Topic 1
Topic 1 After final acceptance, which of the following would the project manager use to assess the strengths and weaknesses of the project?
A. Post-project review
B. Transition plan
C. Project kick-off meeting
D. Quality analysis
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 9
Topic 1
Topic 1 A cause and effect diagram can also be called:
A. a control chart.
B. a scatter diagram.
C. an Ishikawa diagram.
D. a Pareto Chart.
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 10
Topic 1
Topic 1 A project manager is performing activity sequencing using the arrow diagramming method (ADM). Which of the following is true of ADM?
A. ADM can only represent finish to start dependencies.
B. ADM cannot represent multiple successor activities.
C. ADM can only represent activities that are on the critical path.
D. ADM uses boxes representing activities, and arrows to represent dependencies.
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 11
Topic 1
Topic 1 Which of the following risk response strategies involves shifting the negative impact of a threat, along with ownership of the response, to a third party?
A. Risk transfer
B. Risk avoidance
C. Risk sharing
D. Risk mitigation
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 12
Topic 1
Topic 1 To ensure that project status meetings are effective and productive, the project manager should:
A. invite only team members who have an immediate task on the project.
B. publish an agenda prior to the meeting.
C. invite all stakeholders and the sponsor to every meeting.
D. hold only one meeting per week.
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 13
Topic 1
Topic 1 Which of the following would be a direct output of the initiating process group? (Select Two).
A. Project charter
B. Project management plan
C. Statement of Work (SOW)
D. Work Breakdown Structure (WBS)
E. Preliminary scope statement
Answer:
A E
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 14
Topic 1
Topic 1 A project can be defined as which of the following?
A. A high level cost estimate
B. An ongoing work assignment
C. A temporary endeavor with unlimited time or cost for completion
D. A temporary endeavor limited by time or cost
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 15
Topic 1
Topic 1 Which of the following elements would be needed to prepare an effective project scope document?